EnergySaturday, November 21
Customers and nonprofits sue SDG&E over the $1.62 billion Golden Pacific Powerlink
The SDtoday team
If you pay an SDG&E bill, this one's about you. Customers and consumer groups sued Thursday in San Diego County Superior Court. They accuse SDG&E and the California Independent System Operator (CAISO) of colluding to hand SDG&E a 153-mile, 500-kilovolt line it lost in competitive bidding.
SDG&E's bid ran higher than the winner's
Source: Imperial Valley Press Online
View as table
| Value | |
|---|---|
| Horizon West bid | $1,004 million |
| SDG&E bid | $1,620 million |
The suit says CAISO awarded the project in April 2024 to Horizon West Transmission, then approved a split in August 2025 that sent the main line to SDG&E. Horizon West is named as a participant but isn't a defendant.
$900 millionin unnecessary charges the suit says ratepayers would face
Utilities recover transmission costs through customer rates. The suit says the deal inflates the project's capital cost by more than 60%.
- SDG&E's bid ranked last on cost, the suit says
- Plaintiffs include Borrego Community Development Corp. and Anza-Borrego Foundation
- They ask the court to void the transfer
SDG&E said it hasn't been formally served and isn't in a position to comment. Energy engineer Bill Powers, a plaintiff, said the group isn't seeking money and wants to void the award and start from scratch.